Jawaharlal Nehru Urban Renewal Mission (JNNURM)
- More than 14.5 lakh houses sanctioned all over the country (14,59,272).
- 1304 projects of affordable housing and basic amenities to the urban poor with outlay of more than Rs 33,860 crores approved.
- Additional Central Assistance (Grant) of Rs. 18,500 crores committed (representing more than 100% of the 7-year allocation initially provided for 2005-12)
- Additional Central Assistance (ACA) of Rs 7192.02 crores released to States/UTs.
- 63 Mission cities covered under BSUP & 761 cities/towns covered under IHSDP.
- About 3.81 lakh houses in progress and 1.65 lakh dwelling units completed as against the mid-term target of 5 lakhs units in progress.
- Progress of 3 key pro-poor reforms (Land reservation for urban poor, earmarking of municipal budget for the urban poor and implementation of 7-Point Charter for the urban poor and under JNNURM largely on track.
- Financial support for setting up of 23 Programme Management Unit (PMU) at State level in 23 States/UTs approved.
- Financial Support for setting up of 101 Project Implementation Units (PIUs) at Urban Local Body (ULB) level approved.
- An Online JNNURM tracking system as part of Integrated Poverty Monitoring System is developed and is under implementation
- A framework for Third Party Inspection and Monitoring established and agencies for Third Party Inspection and Monitoring empanelled by Mission Directorate. Detailed guidelines have been issued to States.
- States have been exhorted to start preparations for social audit of projects under BSUP & IHSDP. All detailed project reports and minutes of BSUP & IHSDP have been put on the website to establish transparency and sharing of information.
- A Toolkit on comprehensive capacity Building programme has been developed and circulated to all State/UT Governments. Financial assistance is being provided for skill training, capacity building, and City/State urban resource centres.
- More than 90 capacity building/handholding programmes have been conducted across the country and more than 12,000 State/parastatals/local body officials trained in project formulation, design, implementation and monitoring.
Cumulative Physical Progress (As on 31.10.2009)
|
BSUP |
IHSDP |
Total |
|
| No of projects approved |
462 |
842 |
1304 |
| No of States/UTs covered |
31 |
30 |
|
| No of Cities/Towns covered |
63 |
761 |
824 |
| No of DUs approved |
995183 |
464089 |
1459272 |
| No. of DUs on which construction started |
293674 |
88235 |
381909 |
| No. of DUs completed |
122981 |
42570 |
165551 |
Cumulative Financial Progress (As on 31.10.2009)
|
|
Commitment & Release (in Crores) |
||
|
BSUP |
IHSDP |
Total |
|
| Revised Allocation |
16356.35 |
6828.31 |
23184.66 |
| ACA Commitment |
12807.32 |
5692.08 |
18499.40 |
| % Commitment |
78.30% |
83.36% |
79.80% |
| Release |
4212.31 |
3000.87 |
7213.18 |
| % Release (Release vs Commitment) |
32.72% |
52.72% |
39.00% |
| Total project cost approved |
25342.77 |
8517.45 |
33860.22 |
- Progress on 3 Pro-Poor Key Reforms under JNNURM (BSUP & IHSDP)
- Progress of 3 key reforms largely on track
- Internal earmarking within local body budgets for Basic Services to the Urban Poor: 48 cities have undertaken implementation of this reform
- Earmarking of at least 20-25% of developed land in all housing projects (both public and private agencies) for EWS/LIG category:
- 17 States (43 Cities) have issued the policy directives to reserve developed land in public and/or private housing projects
- Implementation of 7- Point Charter: Provision of 7 Basic Entitlements/Services:
- This reform is to be implemented in a staggered manner over the Mission Period in convergence with the programmes of other Ministries as this is also an outcome of the Mission.