MMRDA Skywalks List
PROPOSED SKYWALKS IN MUMBAI METROPOLITAN REGION (MMR)
|
No. |
Station |
Scope of Works |
Proposed Agency |
MMRDA Div. & Concerned Officer / Status |
|
|
MSRDC SKYWALKS |
|||||
|
SKYWALKS WORKS IN PROGRESS |
|||||
|
1 |
Chinchpokali | Skywalk connecting existing Railway’s Foot Over Bridge to Ambedkar Road at the East Side of Station. (4.88 meters wide x 200 meter long) |
MSRDC |
||
|
2 |
Parel | Skywalk connecting East & West side of the Station (with landing at all platforms). 4.88 meters wide x 120 meters long) |
MSRDC |
||
| Skywalk (at Mumbai end) connecting existing Railway’s Foot Over Bridge to Ambedkar Road (at East Side).(4.88 meter wide x 200 meters long) |
|
||||
|
3 |
Reay Road | Skywalk across D’Mello Road (at Kurla end) a landing at all Platforms.(3.66 meters wide x 100 meters long) |
MSRDC |
||
|
4 |
Sewri | Skywalk connecting Railway’s Foot Over Bridge to Public Foot Over Bridge (of D’Mello Road). (3.66 meters wide x 100 meters long) |
MSRDC |
||
|
5 |
Wadala Road | Skywalk across ‘P’ D’Mello Road & connecting existing Railway’s Foot Over Bridge of the Station (at Kurla end) (4.88 meters wide x 125 meters long) |
MSRDC |
||
|
6 |
Vasai Road (W) | Construction of skywalk |
MSRDC |
||
|
7 |
Goregaon (W) | Construction of skywalk |
MSRDC |
||
|
8 |
Vileparle (W) | Construction of skywalk |
MSRDC |
||
|
9 |
Kandivali (E) | Construction of skywalk |
MSRDC |
||
|
10 |
Lowerparel-Currey road walkway (E) | Construction of skywalk |
MSRDC |
||
|
11 |
Grant Road | Construction of skywalk |
MSRDC |
||
|
12 |
Masjid Stn area (W) | Construction of skywalk |
MSRDC |
DROPPED | |
|
13 |
Naigaon | Construction of skywalk |
MSRDC |
DROPPED | |
|
14 |
Sand Hurst Road | Skywalk connecting from (South side of) Hankok Bridge (at the West side of track) to the platform No.1 & 2 of the station. (3.66 meters width x 100 meters long) |
MSRDC |
DROPPED | |
|
KDMC SKYWALK |
|||||
|
SKYWALKS WORKS IN PROGRESS |
|||||
|
15 |
Kalyan (W) | Skywalk connecting existing Railway’s FOB (Under Construction) to Valli Peer Road (Kalyan Stn Rd at West end) and also to Kolsawadi side (at East end).(4.88 m wide x 250 m long) |
KDMC |
||
|
16 |
Kalyan (E) | Construction of skywalk |
KDMC |
||
|
MMRDA SKYWALKS |
|||||
|
SKYWALK COMPLETED |
|||||
|
17 |
Bandra (E) to Kalanagar | Construction of skywalk |
MMRDA |
||
|
18 |
Kanjurmarg (E) | Construction of skywalk |
MMRDA |
||
|
19 |
Bandra (E) | BA local station to Kalanagar – Kherwadi- Extension |
MMRDA |
||
|
20 |
Dahisar (W) | Construction of skywalk |
MMRDA |
||
|
21 |
Badlapur (W) | Construction of skywalk |
MMRDA |
||
|
22 |
Mira Road | Construction of skywalk |
MMRDA |
||
|
SKYWALKS WORKS IN PROGRESS |
|||||
|
23 |
Virar (W) | Construction of skywalk |
MMRDA |
||
|
24 |
Virar (E) | Construction of skywalk |
MMRDA |
||
|
25 |
Bandra (W) | Construction of skywalk |
MMRDA |
||
|
26 |
Andheri (E) | Construction of skywalk |
MMRDA |
||
|
27 |
Santacruz (E) | Construction of skywalk |
MMRDA |
||
|
28 |
Ulhasnagar (E) | Construction of skywalk |
MMRDA |
||
|
29 |
Ulhasnagar (W) | Construction of skywalk |
MMRDA |
||
|
30 |
Bhandup (W) | Construction of skywalk |
MMRDA |
||
|
31 |
Vidyavihar (E) | Construction of skywalk |
MMRDA |
||
|
32 |
Vidyavihar (W) | Construction of skywalk |
MMRDA |
||
|
33 |
Kurla (E) | Construction of skywalk |
MMRDA |
||
|
34 |
Ghatkopar (W) | Construction of skywalk |
MMRDA |
||
|
35 |
Thane (E) | Construction of skywalk |
MMRDA |
||
|
36 |
Bhayander (W) | Construction of skywalk |
MMRDA |
||
|
37 |
Mulund (W) | Construction of skywalk |
MMRDA |
||
|
38 |
Badlapur (E) | Construction of skywalk |
MMRDA |
||
|
39 |
Bhayander (E) | Construction of skywalk |
MMRDA |
||
|
40 |
Borivali (W) | Construction of skywalk |
MMRDA |
||
|
41 |
Chembur | Construction of skywalk |
MMRDA |
||
|
42 |
Dadar (E) Pt II | Construction of skywalk |
MMRDA |
||
|
43 |
Dadar – (E) Pt III | Construction of skywalk |
MMRDA |
||
|
44 |
Dahisar (E) | Construction of skywalk |
MMRDA |
||
|
45 |
Santacruz (W) | Construction of skywalk |
MMRDA |
||
|
46 |
Mulund (E) | Construction of skywalk |
MMRDA |
DROPPED | |
|
47 |
Dadar (E) Pt I | Construction of skywalk |
MMRDA |
DROPPED | |
|
48 |
Kurla (W) | Construction of skywalk |
MMRDA |
DROPPED | |
|
49 |
Ambernath ( E) | Construction of skywalk |
MMRDA |
||
|
50 |
Ambernath ( W) | Construction of skywalk |
MMRDA |
||
|
51 |
Vikhroli (E) | Construction of skywalk |
MMRDA |
APPROVAL 22 Aug 2008 | |
|
52 |
Vikhroli (W) | Construction of skywalk |
MMRDA |
APPROVAL 22 Aug 2008 | |
|
53 |
Mahim (W) | Construction of skywalk up to Mahim Dargah via Mahim Church |
MMRDA |
APPROVALS 18 SEP 2008 | |
|
54 |
Mahalaxmi (W) | Construction of skywalk up to Mahalaxmi Temple |
MMRDA |
APPROVALS 07 Oct 2008 | |
|
55 |
Khada Parsi Statue | Construction of skywalk up to Nisbit Junction |
MMRDA |
Sanjay Barve, IPS, Jt CP Traffic | |
|
56 |
Sion | Construction of skywalk up to Dharavi 90` Road and EEH |
MMRDA |
Sanjay Barve, IPS, Jt CP Traffic | |
|
57 |
Ghatkopar (E) | Construction of skywalk |
MMRDA |
||
|
58 |
Mahim (E) | Construction of skywalk up to Mahim Badi Masjid |
MMRDA |
APPROVALS 25 SEP 2008 DROPPED | |
|
TENDERS TO BE INVITED BY ENGINEERING DIVISION |
|||||
|
59 |
Mankhurd | Construction of skywalk up to Lallu Bhai Compound |
MMRDA |
Sh. Kapil Patil MLA | |
|
60 |
Shahad (E) | Construction of skywalk at Shahad (E) |
MMRDA |
Suresh ( Pappu) Kalani, MLA | |
|
61 |
Shahad (W) | Construction of skywalk at Shahad (W) |
|
Suresh ( Pappu) Kalani, MLA | |
|
62 |
Dadar | Construction of East-West connector skywalk along Tilak Bridge |
MMRDA |
Sanjay Barve, IPS, Jt CP Traffic. | |
|
63 |
Vithal Vadi (E) | Construction of skywalk up to Pawai Chowk |
MMRDA |
Suresh (Pappu) Kalani, MLA | |
|
64 |
Vithal Vadi (W) | Construction of skywalk up to Vyapari Gali |
MMRDA |
Suresh (Pappu) Kalani, MLA . | |
|
65 |
Matheran | Construction of skywalk from Aman Lodge to Sakha Ram Tuka Ram point |
MMRDA |
Matheran Nagaradhaykhs | |
|
66 |
Komothe (Navi Mumbai) | Construction of skywalk |
MMRDA |
Ajit Pawar MLA | |
|
67 |
Vashi (Navi Mumbai) | Construction of skywalk |
MMRDA |
Ajit Pawar MLA | |
|
DROPPED AT PLANNING STAGE |
|||||
|
68 |
CST to Churchgate | Construction of skywalk |
MMRDA |
Dropped | |
|
69 |
Churchgate to Mantralya | Construction of skywalk |
MMRDA |
Dropped | |
|
70 |
Vidhan Bhavan to Regal Cinema | Construction of skywalk |
MMRDA |
Dropped | |
|
71 |
Regal Cinema to CST | Construction of skywalk |
MMRDA |
Dropped | |
NEW PROPOSALS
|
72 |
Marine Lines | Construction of skywalk up to Vardhman Chowk |
MMRDA |
Atul H Shah, Ex MLA |
|
73 |
Nariman Point | Construction of skywalk up to Colaba |
MMRDA |
Annie Shekhar, MLA |
|
74 |
Marine Lines | Construction of skywalk up to Kalba Devi Road Junction |
MMRDA |
Raj Purohit, MLA |
|
75 |
Mantralya | Construction of skywalk up to Nariman Point and CST |
MMRDA |
Raj Purohit, MLA |
|
76 |
Matunga | Construction of skywalk up to Wadala |
MMRDA |
Jaganath Shetty MLA |
|
77 |
Mithi Bai College | Construction of skywalk up to Centaur Hotel |
MMRDA |
Ashok Bhau Jadhav MLA |
|
78 |
Vile Parle (E) | Construction of skywalk |
MMRDA |
|
|
79 |
Borivali (E) | Construction of skywalk |
MMRDA |
Gopal Shetty, MLA |
|
80 |
Jogeshwari | Construction of skywalk at Jogeshwari |
MMRDA |
MCGM |
|
81 |
Worli Naka | Construction of skywalk up to Poddar Hospital |
MMRDA |
Sachin Ahir, MLA |
|
82 |
Varsova Jetty | Construction of skywalk up to Madh Jetty |
MMRDA |
Baldev Khosla, MLA |
|
83 |
Usha Nagar, Bhandup (W) | Construction of skywalk |
MMRDA |
Housing Society Sanjay Deena Patil ,MP |
|
84 |
Panvel | Construction of skywalk up to Baba Saheb Ambedkar Statue |
MSRDC |
Parshant Thakur Nagaradhyaksh |
|
85 |
Panvel Bus Stand | Construction of skywalk from Hotel Smarat to NH4 |
MSRDC |
Parshant Thakur Nagaradhyaksh |
|
86 |
Malad (E) | Construction of skywalk up to Pushpa Park |
MMRDA |
Suchitra Naik Nagarsewika and Sunil Parbhu Sabha Grayha Neta MCGM |
|
87 |
Malad (W) | Construction of skywalk up to Mahila College |
MMRDA |
Suchitra Naik Nagarsewika and Sunil Parbhu Sabha Grayha Neta MCGM |
|
88 |
Goregaon (E) | Construction of skywalk Goregaon (E) |
MSRDC |
Mr Subash Desai , MLA |
|
89 |
Khapoli | Construction of skywalk Khapoli Rly Stn to Police stn, Shashtri Nagar |
|
Mr Devender Sattam , MLA |
|
90 |
Vasai Road (E) | Construction of skywalk Vasai Road (E) up to CIDCO office |
|
Mr D B Shingda , MP |





















Skywalk over railway crossing at Vikhroli East to West is urgently required as more railway accedent has been reporting and St. Joseph High School is very much near to the track. As it is goodnew that two skywalk has been approved for east and west, Will you intimate whether skywalk connect east and west (Vikhroli). I would be very much grateful if you intimate the same. Various proposals of sky walk will defenetiely help people from congestion.
Thanking you.
ambernath cha skywalk kadhi chalu honar 1 varsha zale kam chalu ahe??
ambernath skywalk kadhi chalu honar..
proposed skywalk at vidyavihar needs exits at vidyavihar bus depot, mig colony, somaiya gate.
When is the Goregaon Skywalk going to be completed?. My shop & our Building is completely surrounded by the raw material dumbped by the J.Kumar people. Rats Die, Garbage is thrown on it… Keeps on smelling the whole day. What the hell is happening… If they dont want to complete the Skywalk, then why the hell do they initiate such a burden on Public Road….????
Till date the sky walk built by MMRDA at Badlapur from east to west has not been connected, thereby making difficult to the commuters and it is a waste of money if it is not connected. Why it is not connected and when it is expected to be connected
we need sky walk for vikhroli east and west becoz accidents are happening every day
We require a sky walk adjacent to the existing foot overbride connecting platform No.7 to Lokgram. The existing FOB is fully packed during morning and evening hours . Increase in population in eastern side has immensely increased the pressure on the existing FOB. besides the existing FOB is in a very pathetic condition with all tiles broken. Immediate steps should be taken to replace the tiles. The tiles earlier laid on the FOB is of very poor quality and of inferior grad. please replace it with good quality tiles and guarantee of the contractor to be obtained that the tiles will last for a minimumperiod of 10 years.
It is urgently requested that the Sky Walk from Badlapur East to West is not still connected. Already more than three years have lapsed and the same is still pending even after assurances given so many times for connecting the same. Since day to day public has increased, it is requested to connect the same at the earliest